Let Me Tell You About The Use And Construction Methods Of The Biaxial Geogrid
Biaxial geogrid construction method: excavate the foundation bed, set up a sand cushion (the height difference is not more than 10cm), roll it into a platform, and lay the grid. The longitudinal axis should be consistent with the main force direction, and the longitudinal overlap should be 15-20cm , Horizontal 10cm, lap joints are bound with plastic tape, and fixed on the ground with U-shaped nails every 1.5-2m on the laid grid. The laid geogrid should be backfilled with earth material in time, and the laid geogrid layer Digital vision technical requirements.